Mullanphy Emigrant Home Stabilization Work Making Progress

by Michael R. Allen

The photograph above shows the state of the Mullanphy Emigrant Home today. Workers resumed masonry work yesterday and today will likely have the roof resting on a solid east supporting wall for the first time since last April.

After the south and east walls are laid in block, workers from John Smith Masonry will move to the building’s north end, where another collapsed wall section remains. After that work is finished, further work — including laying face brick and replicating limestone ornament — will come either through a development plan or further donations.

The Old North St. Louis Restoration Group still needs donations to cover expenses related to the stabilization project. While the masons have kindly donated labor and materials, the Restoration Group continues to pay builder’s risk insurance on what has been a lengthy (and risky) wall rebuilding project. Please visit SaveMullanphy.org for information on making a donation.